Judge allows preliminary Keystone XL work

Associated Press

A Montana judge says a Canadian company may continue preliminary work on the proposed Keystone XL oil pipeline while his order blocking construction is in effect.

U.S. District Judge Brian Morris said Nov. 28 he will clarify his Nov. 8 injunction to allow TransCanada to conduct engineering and planning activities, confirm shipper contracts, meet with different groups and acquire equipment, permits and land rights.

On Nov. 8, Morris blocked TransCanada’s permit to build the pipeline from Alberta’s oil sands through a half-dozen U.S. states to the Gulf of Mexico. The judge ordered a new environmental review after saying the Trump administration had not fully considered the effects of the pipeline.

TransCanada had argued it wants to keep that preliminary work on schedule that that it can be prepared to start pipeline construction as early as mid-February. - ASSOCIATED PRESS





Copyright 2003 Associated Press. All rights reserved. This material may not be published, broadcast, rewritten, or redistrubuted.

Petroleum News - Phone: 1-907 522-9469
[email protected] --- https://www.petroleumnews.com ---
S U B S C R I B E

Copyright Petroleum Newspapers of Alaska, LLC (Petroleum News)(PNA)Š1999-2019 All rights reserved. The content of this article and website may not be copied, replaced, distributed, published, displayed or transferred in any form or by any means except with the prior written permission of Petroleum Newspapers of Alaska, LLC (Petroleum News)(PNA). Copyright infringement is a violation of federal law.